Nordic nuclear output Tuesday: 10,862 MW (88%)
(Montel) Nordic nuclear power production is running at 10,862 MW on Tuesday morning, down 1 MW from Monday, with reactors using 88% of installed generation capacity (12,283 MW).
OKG has restarted Oskarshamn 3 over the weekend, after the unit was put on hot standby between Wednesday and Saturday last week to perform necessary maintenance work. The operator has also dropped earlier plans to operate the reactor at a reduced output of 0-400 MW for most of this week.
Ringhals 2 is offline for annual maintenance until late November, while Oskarshamn 2 is offline for a major safety upgrade until 1 September 2015.
Figures updated at 06:50 CET.
Nuclear plant | Current output (MW) | Change* (MW) | Utilisation** | Installed capacity (MW) | Annual outage starting | Annual outage ending |
Forsmark 1 | 992 | 0 | 101% | 984 | 03.05.15 | 11.06.15 |
Forsmark 2 | 1133 | 3 | 101% | 1120 | 05.07.15 | 20.07.15 |
Forsmark 3 | 1179 | -4 | 101% | 1170 | 02.08.15 | 22.09.15 |
Oskarshamn 1 | 454 | 0 | 96% | 473 | 06.04.15 | 22.05.15 |
Oskarshamn 2 | 0 | 0 | 0% | 638 | 01.06.13 | 01.09.15 |
Oskarshamn 3 | 1449 | 5 | 104% | 1400 | 24.05.15 | 13.06.15 |
Ringhals 1 | 880 | 1 | 100% | 878 | 12.04.15 | 08.06.15 |
Ringhals 2 | 0 | 0 | 0% | 865 | 15.08.14 | 25.11.15 |
Ringhals 3 | 1064 | -2 | 100% | 1063 | 20.05.15 | 25.06.15 |
Ringhals 4 | 936 | -2 | 100% | 940 | 12.08.15 | 17.09.15 |
TOTAL SWEDEN | 8087 | 1 | 85% | 9531 | ||
Olkiluoto 1 | 880 | -3 | 100% | 880 | 03.05.15 | 13.05.15 |
Olkiluoto 2 | 890 | 5 | 101% | 880 | 17.05.15 | 01.06.15 |
Loviisa 1 + 2 | 1005 | -4 | 101% | 992 | 09.08.15 | 26.08.15 |
29.08.15 | 15.09.15 | |||||
TOTAL FINLAND | 2775 | -2 | 101% | 2752 | ||
TOTAL NORDIC | 10862 | -1 | 88% | 12283 |
* Change from previous working day
** Rounded figures
anton@montel.no
06:56, Tuesday, 20 January 2015